If you are making the case for coordination support or a new tool, someone will reach for a number: construction teams lose fourteen hours a week. The figure comes from a real report. It is also a 2018 survey composite of three different activities, and it is often quoted as something it is not.

The published research is broader than that one survey. Surveys report what people estimate. Timesheet, interview and observation studies record what staff and crews did under stated conditions. Process studies track how long a drawing waits. Each answers a different question.

Our review did not establish a current, representative weekly avoidable-loss rate across virtual design and construction (VDC), mechanical, electrical and plumbing (MEP) coordination, detailing and fabrication roles. That is a finding about the evidence we reviewed, not proof that no such study exists. Below is what the evidence does support, and a question list for testing any statistic.

The evidence at a glance

Read each row across before quoting a figure; the last column matters as much as the number.

Surveys: what respondents estimated

SourceWho and howFigureWhat it countsDo not read it as
PlanGrid and FMI, 2018[1]599 construction leaders; self-estimated weekly hours; vendor-sponsored14.1 hours a weekSearching for information, resolving disagreements, and mistakes and rework, combinedA measured rework rate or recoverable savings
Deloitte Access Economics for Autodesk, 2023[2]1,275 organizations; managers and executives11.5 hours a weekResearching and analyzing dataLost time
Autodesk, 2025[3]3,503 leaders and experts in 27 countries13 hours a week, meanRespondents' own time looking for dataA rise since 2018

Office and detailing work: recorded or reconstructed

SourceWho and howFigureWhat it countsDo not read it as
Sacks and Barak, 2006[4]Staff timesheets from 52 precast and 14 cast-in-place projects, plus experimentsRecorded hours by activityEngineering, detailing and draftingA weekly avoidable-loss rate
Josephson and Saukkoriipi, 2005[5]Five architects and five technical consultants, each observed for one day at two-minute intervalsActivity shares; no measured design-waste rateDesign-office workProof that designers' waste was measured
Yoo and Ham, 2020[6]Four documentation staff on one plant-facility steel project; hours reconstructed in interviewsMinutes per fabrication drawing, two-dimensional (2D) versus three-dimensional (3D)First-issue drawings; repeated design changes excludedStopwatch timing or an industry benchmark

Site work: observed

SourceWho and howFigureWhat it countsDo not read it as
Josephson, 1998[7]Trained observers on seven Swedish building projects, mid-1990s7.1% of labor hoursCorrecting 2,879 site defectsOffice time or a weekly figure
Seppänen and Görsch, 2022[8]15 MEP workers and foremen on four Finnish projects; helmet video and interviewsDirect work: 24% for electricians, 15% for plumbers and heating, ventilation and air-conditioning installersShare of 170 analyzed video hoursProof that the remainder was waste
Holth, Fosse and Drevland, 2026[9]One 11-person carpentry crew on one Norwegian project; 854 observations41.31% direct, 47.89% indirect, 10.80% wastedWork-sampling observations over five daysA population estimate

Process flow: elapsed time and estimates

SourceWho and howFigureWhat it countsDo not read it as
Freire and Alarcón, 2000[10]Four projects at one design firm; drawing cycle times measuredDrawings worked on for 31.7% of their cycle timeA drawing's elapsed cycle timeStaff idle for the rest
Chin, 2009[11]29 shop-drawing reviews at one engineering firm, 200855.82 hours, mean review timeElapsed hours from stamp-in to stamp-outReviewer labor, or seven calendar days
Nath and colleagues, 2015[12]Precast shop drawings; project records, a pilot and practitioner estimatesEstimated 36% processing-time and 38% total-time improvementA proposed future workflowAn observed saving

What the 14.1 hours contains

PlanGrid and FMI asked 599 construction leaders how many hours a week they spent on six activities. Three were classed as non-optimal: 5.5 hours searching for project information, 4.7 hours resolving conflicts, and 3.9 hours dealing with mistakes and rework. Together they make 14.1.[1]

Three details change how the figure can be used:

  • Rework is 3.9 of the 14.1 hours. The rest is searching and conflict resolution.[1]
  • Conflict here means disagreements among project participants, not model clashes.[1]
  • The often-quoted 35% is 14.1 of the 40.5 hours respondents allocated across the six activities, not a share of a measured work week.[1]

The 19 VDC managers in the sample reported 14.42 hours.[1] A group of 19 cannot stand in for VDC managers in general.

Three surveys, three questions

Deloitte Access Economics' 2023 report for Autodesk found that management and executive employees spent 11.5 hours a week researching and analyzing data. The report calls an unquantified part of that time inefficient; it does not call the whole 11.5 hours lost.[2] Analysis is often the job.

Autodesk's 2025 report asked respondents about their own weekly time looking for data and reported a mean of 13 hours. Digitally advanced respondents reported two fewer hours.[3] That is a difference between groups, not the measured effect of buying software.

Different questions, samples and years mean these surveys cannot be averaged into one range. A move from 5.5 hours searching in 2018 to 13 hours looking for data in 2025 is not a trend either. Each figure belongs in a sentence with its own question, population and year.

Office and detailing work has been measured

It is sometimes said that nobody has measured detailers or design staff. Earlier drafts of our own review made that mistake.

Sacks and Barak drew engineering, detailing and drafting hours from staff timesheets on 52 precast and 14 cast-in-place projects, then compared them with modeling experiments. The authors note differences in skills and conditions between the office baseline and the experiments, and they excluded design-change hours from the comparison.[4]

Josephson and Saukkoriipi followed five architects and five technical consultants for one working day each, noting activity every two minutes. They recorded interruptions, waiting and some rework.[5]

Yoo and Ham compared 2D and 3D fabrication documentation on one plant-facility steel project. Working hours were reconstructed through interviews with engineers who did the work, not timed task by task, and repeated design changes were excluded.[6]

These studies record real work. None supplies a current weekly rate of avoidable loss for a coordinator, detailer or fabrication administrator.

Site studies separate support from waste

Josephson's defect research placed trained observers on seven Swedish building projects. They followed 2,879 defects and reported 22,000 correction hours, 7.1% of the labor hours worked in the study periods. The cost assessment included estimates.[7]

Newer observation shows why time outside direct work cannot simply be called waste. In Seppänen and Görsch's helmet-camera study, direct installation was a minority of analyzed time. The rest included discussion, hauling, searching and preparation. The authors traced most of the waste they did identify to missing prerequisites, such as materials, unfinished preceding work and missing design information.[8]

The sample was selected by availability during pandemic restrictions. The authors also note that their direct-work shares are lower than work sampling usually reports, and that the difference in method may explain part of the gap.[8]

Holth, Fosse and Drevland's five days of work sampling on one carpentry crew found that indirect work, mainly preparation and transport, was the largest category and wasted work the smallest.[9] It is one project, not a population estimate.

A waiting drawing is not an idle person

Flow studies measure how long work takes to move, not how long people sit still.

In Freire and Alarcón's study of four projects at one design firm, drawings were being worked on for 31.7% of their cycle time and spent the rest waiting between stages.[10] During that wait, the designer may well have been working on another drawing.

Chin's study logged 29 engineering reviews of shop drawings at one engineering firm over about seven months. The mean was 55.82 elapsed hours from stamp-in to stamp-out. The paper presents it as 6.98 days by dividing by eight, so it is neither seven calendar days nor reviewer labor. The author concluded that the root cause of long reviews was insufficient and unclear information rather than reviewer capability or availability.[11]

Nath and colleagues estimated a 36% processing-time and 38% total-time improvement for a re-engineered precast shop-drawing process. Parts were validated in a workshop and a pilot, the future workflow was estimated by experienced precasters, and whole-workflow validation was outside the study.[12] It is a labeled estimate, not an observed saving.

Test a statistic before it goes into a business case

The questions below are Atlas's checklist, drawn from the distinctions above. Apply them to any figure, including the ones in this article.

  1. Whose hours: which roles, trades, country and year?
  2. How were they obtained: self-estimate, timesheet, observation, interview reconstruction or projection?
  3. Does one total combine several different activities?
  4. What is the denominator: a paid week, a drawing's cycle time, project labor hours or cost?
  5. Is the time necessary work, such as review, coordination, legitimate search or an owner-directed change?
  6. How many people or items sit behind the figure, and is any subgroup small?
  7. Who sponsored the study, and do they sell something related to the result?
  8. Did the study measure a change, compare groups, or estimate a future workflow?
  9. Does using it as weekly hours require an assumption you would have to state?
  10. Would the released time become cash, or only capacity for other work?
  11. Can a reviewer open the source and find the page?

Use the research to decide what to measure

Sources

  1. PlanGrid and FMI, Construction Disconnected, 2018, pp. 4–5, 11–14. Original report. Supports the sample, activity definitions, the three parts of the 14.1-hour composite and the VDC-manager subgroup figure; self-estimated and vendor-sponsored, so it does not show measured or recoverable hours.
  2. Deloitte Access Economics for Autodesk, State of Data Capabilities in Construction, 2023, pp. 34, 39. Report. Supports 11.5 weekly hours researching and analyzing data, and the survey method; does not quantify lost time.
  3. Autodesk, 2025 State of Design & Make: Spotlight on Construction, 2025, pp. 2, 10, 24. Publisher-hosted report. Supports the 13-hour mean for looking for data and the group difference; does not support a trend from 2018 or a causal software effect.
  4. Sacks and Barak, Quantitative Assessment of the Impact of 3D Modelling of Building Structures on Engineering Productivity, 2006, pp. 1190–1193. Proceedings paper. Supports timesheet-recorded engineering, detailing and drafting hours; its experimental comparisons carry the authors' own caveats and are not a weekly waste rate.
  5. Josephson and Saukkoriipi, Slöseri i byggprojekt: Behov av förändrat synsätt (Waste in construction projects: the need for a changed approach, in Swedish), FoU-Väst report 0507, 2005, p. 27. Report. Supports the one-day observation of five architects and five technical consultants, the authors' caution about classifying design work, and that their design-waste share is assumed; does not supply a measured designer-waste rate.
  6. Yoo and Ham, Productivity Analysis of Documentation Based on 3D Model in Plant Facility Construction Project, Applied Sciences 10(3), 1126, 2020, p. 8. Journal article. Supports a 2D-versus-3D documentation comparison with interview-reconstructed hours on one project; not independent timing or a general benchmark.
  7. Josephson, Defects and Defect Costs in Construction, 1998, pp. 2–3; related journal article with Hammarlund, 1999. Working paper. Journal record. Supports the seven-project defect study and the 7.1% correction-labor share; historical site work, not office hours.
  8. Seppänen and Görsch, Decreasing Waste in Mechanical, Electrical and Plumbing Work, 2022, pp. 86–88, 93. Proceedings record. Full paper. Supports helmet-camera observation, activity shares and the missing-prerequisite findings; a convenience sample, not a wasted-time rate.
  9. Holth, Fosse and Drevland, Carpenters' Workday: Between Value-Adding Work and Physical Strain, 2026, pp. 1268–1270. Proceedings paper. Supports one crew's work-sampling shares on one Norwegian project; not a population estimate.
  10. Freire and Alarcón, Achieving a Lean Design Process, 2000, Figure 5 and discussion. Proceedings record. Full paper. Supports drawing cycle-time utilization at one design firm; measures a drawing's elapsed time, not staff idle time.
  11. Chin, Identifying Root Causes of Long Review Times for Engineering Shop Drawings, 2009, pp. 557–559, 570. Proceedings paper. Supports the 29-review sample, the 55.82 elapsed-hour mean and the information-quality finding; does not measure reviewer labor or idle time.
  12. Nath and colleagues, Productivity Improvement of Precast Shop Drawings Generation Through BIM-Based Process Re-Engineering, Automation in Construction 54, 2015, pp. 55–56, 67. Publisher record (DOI). Supports a partly validated, prospective workflow estimate; not an observed whole-process saving.

SCOPE

Atlas Construction Consultants is a construction technology consultancy. This article is a bounded review of published research, not a systematic census of every study, and Atlas has not collected client measurements for it. Fourteen further candidate claims from the review are withheld from public numerical use because they could not be checked against the original texts.

← Back to all articles